Project: Demolition of former Speedway stadium.
This demolition project comprised the following works:-
- Demolition of Grandstand and buildings extending to c. 1600 sq m
- Full clearance of a 34,000 sq m site
- Break up and processing of the slab and foundations for crushing
- Crushing of the hardcore to 6f2 left on site for reuse.
We completed this project in 4 weeks, a week ahead of schedule.